Wollar Road Closure

Wollar road.JPG
A section of Wollar Road will be closed for ten weeks from 10 January to realign two dangerous curves as part of the three-year road safety upgrade.
 
Wollar Road will be closed through the Munghorn Gap Nature Reserve. A detour will be in place via Ulan Wollar Road. The closure will be in place between the Castle Rocks car park and Cumbo Road (see below). 
 
The closure of Wollar Road is expected to commence at 7am Monday, 10 January for ten weeks, with an anticipated reopening on Monday, 21 March.
 
The road will be closed for the shortest possible time necessary to reduce traffic impacts.
 
There will be some delays as works continue after this period under traffic control. The entire project is expected to be complete by May when traffic will return to normal.
 
These works are part of the $6.8 million Wollar Road Upgrade, jointly funded by Council and the NSW Government through its Restart NSW Fund and Saving Lives on Country Roads programs.
 
Council apologises for any inconvenience and reminds motorists that all temporary speed limits during the construction are enforceable by police.
 
Blasting is expected to take place on the closed section on Thursday, 13 January. 